SR 20 Sharpes Corner Roundabout Construction Timeline

7,112 views

Loading...

Loading...

Transcript

The interactive transcript could not be loaded.

Loading...

Loading...

Rating is available when the video has been rented.
This feature is not available right now. Please try again later.
Published on Mar 20, 2018

Anacortes and Whidbey Island drivers and cyclists should prepare for upcoming construction and lane closures affecting spring and summer trips to the area as crews spend the next three months making road improvements on State Route 20.

On Monday, April 2, Washington State Department of Transportation contractor crews from Tapani, Inc. will start building two new roundabouts near busy intersections on SR 20 that take travelers to Anacortes or Whidbey Island. Crews plan to work around-the-clock to complete major portions of this project by July 2018.

Building these roundabouts will improve safety and reduce delays through these busy intersections

Music Courtesy:
Morning Sun by Nicolai Heidlas Music https://soundcloud.com/nicolai-heidlas Creative Commons — Attribution 3.0 Unported— CC BY 3.0 https://www.youtube.com/redirect?v=Uz...
Music promoted by Audio Library https://youtu.be/UzCFTyluxic

Loading...

When autoplay is enabled, a suggested video will automatically play next.

Up next


to add this to Watch Later

Add to

Loading playlists...