This video displays the speed and ease of a MAXRaft installation on "Good Ground" per NZS 3604.
The time taken to in the video is as follows:
Lay Polythene and tape (lots) of pipes:1.75 hrs
Lay MAXRaft: 1.16 hrs
Lay Steel reinforcing and mesh, chair and lap all perimeter/load bearing beams: 2.5 hrs
An additional 2 hours was spent bracing the perimeter (the house was 211m2 with an 88.39m perimeter).
Battery limitations prevented the videoing of the bracing of the site.
The site had been screeded prior to the arrival of the MAXRaft team, with profiles up and underslab plumbing works completed.