Uploaded on Aug 27, 2009

Aug 27-09: An update on this section. The ROW will be 100% pour up to Northcliff by the weekend with the rest done by next weekend to connect to Phase II subject when TTC splice the last 4 rails.

Curb in place on the south side from Oakwood to Glenholme with hydro being installed. Sidewalk could or should be in place by next weekend so it ready when school starts on the 8th.

Road is 100% marked from Oakwood to Christie waiting some north-south crossing to be done.

More light poles going up as well a few new base for them being built. Pavers are on site and ready to be place for the last 2 blocks.

Traffic will one way or another be shifted this weekend either at Oakwood or Winona so sidewalks can start west from Atlas. TTC would like to see service to Oakwood in late Nov.

Shelters are in various stages of built with one with planter and soil in place. Planter material on site.