Simultaneous Auguring is performed in areas where difficult soils are encountered. Because the fully encased auger is installed at the same time as the sheet pile, the soil is partly sheared by the advancing sheet pile (as pairs) and the passive condition of the soils are nearly unchanged.

With the Simultaneous Auguring system, this method of sheet pile installation is desirable in areas where the N-Values reach from 40 BPF ~ 100 BPF and beyond refusal.