Tough Critical Path Problem PMP Exam Prep

Loading...

Sign in or sign up now!
Alert icon
Upgrade to the latest Flash Player for improved playback performance. Upgrade now or more info.
11,152
Loading...
Alert icon
Sign in or sign up now!
Alert icon
Ratings have been disabled for this video.

Uploaded by on Aug 14, 2010

www.praizion.com for more PMP Mock Exams and realistic PMP Quizzes
PMP Exam practice: network diagram with multiple points of convergence and divergence. Download and solve: http://praizion.com/Downloads/FORMULAMANIA_HOMEWORK.pdf
Let me know if you cracked it!

Forward pass, backward pass, ES, EF, LS, LF, Free slack, total slack.
Project slack: how long can you delay the project's start date without affecting the required or customer imposed due date?

Category:

Education

Tags:

License:

Standard YouTube License

Link to this comment:

Share to:
see all

All Comments (2)

Sign In or Sign Up now to post a comment!
  • Thank you. It was really helpful and well explained!

  • Great lesson, however I am able to be able to calculate the CP but I am still having trouble structuring a network with multiple activities, if you can plug a video or 2 in on composing the network, I would appreciate very much. Thank you.

Loading...

Alert icon
0 / 00Unsaved Playlist Return to active list
    1. Your queue is empty. Add videos to your queue using this button:
      or sign in to load a different list.
    Loading...Loading...Saving...
    • Clear all videos from this list
    • Learn more