In May 2006, Underground Solutions (UGSI) was contracted by Horseshoe Construction to provide Fusible C-905® pipe and fusion services for the slipline repair of a failing concrete water line along heavily traveled Zaragosa Boulevard in El Paso, TX. UGSI provided the pipe and fusion services while Horseshoe Construction did the pipe installation and provided butterfly valves, air/vacuum valves, blow-off installations, reconnections, laterals, and grouting of the annular space. UGSI began work in August 2006 and completed final pressure testing in January 2007.