Train 9122, pushed by DC 4951, enroute to Waitakere is seen here at 1213hrs on Wednesday 3rd March 2010 passing through the temporary track arrangement through the new Avondale station construction site. A temporary construction turnout has been provided to keep trains away from the main work site. When double track is complete, both of these turnouts will be removed. This arrangement came into use on Monday 1st March 2010 as part of the opening of the New Lynn trench.