Asphalt Patching should be done between March 15th and December 15th with some flexibility pending the weather.
Asphalt Paving should be done between April 1st and November 31st.
Seal Coating should be done between April 1st and November 15th.
Striping should be done between March 15th and December 15th.
Crack sealing can be done 12 months a year as long as the pavement is dry.
Concrete work can be performed during the winter as long as the temperature is not expected to drop much below freezing during the first 24 hours. Under certain conditions, additives may added to deter the concrete from freezing.