In March 2011, the Town began the next phase of enhancements to Robert Road from Spouse Drive to Tranquil Boulevard. This project is now approximately half complete.
Crews are busy installing underground
utilities. Construction above ground has begun and roadway improvements
will be more visible in the coming weeks.
Here are some of the improvements
to date:
• Approximately 1,750 feet of new waterline has been installed
• Two fire hydrants have been replaced
and three additional fire hydrants
have been installed
• Approximately 3,000 feet of new storm-drain pipe has been installed
• Curb and gutter enhancements
• Driveway entrances and catch basins
This phase of Robert Road is scheduled
to be completed in early Fall 2011.
Please take caution and plan for delays when traveling through this area.
We appreciate your patience and understanding as we move forward in the development of Robert Road.
For questions regarding this project,
please contact Ray Smith at the Public Works Department by email: rsmith@pvaz.net or phone - (928) 759-3075.