This brief video focuses on the connection of input and output cabling, as well as the installation of fuses and/or circuit breakers in Telects high-current load center panel, an ideal platform for managing power to routers and servers.
See how a double-lug design in the rear of the panel enables the use of higher-voltage cables, helping to maximize the usage of the panel and minimize voltage drop if the load center is a great distance from the power feed.
Other installation tips include:
• Connection of double-pole circuit breakers through the use of a load strap;
• Simple wire connection of GMT fuse outputs;
• Installation of various distribution components, including single-pole and double-pole circuit breakers, TPC fuses and TPS/TLS fuses.
Learn more at Telect.com.