Yeywa Hydro Power Project

Loading...

Sign in or sign up now!
2,902
Loading...
Alert icon
Sign in or sign up now!
Alert icon

Uploaded by on Jul 27, 2008

Yeywa Hydro power Project (2001 to 2010).The third-largest in the world, 134 m high, 2.5M m3 of concrete
The scheme comprises a 134m high RCC gravity dam with a total volume of 2.5M m3 of concrete. Other features include an ungated spillway for a design flood of 6,600m3/s and a 790MW (4 x 197MW) powerhouse at the toe of the dam on the left bank.

The Yeywa project will use four turbines each capable of generating 197.5 MW, giving it a total capacity of 790 MW. The power house for the turbines is 510 feet long, 148 feet wide and 197 feet high. U San Wai said the power house and the dam wall would be able to withstand earthquakes of up to eight on the Richter scale. He said a Swiss company, Colenco Power Engineering, was acting as technical consultant for the project, which is being built by the department and three Chinese companies.
15th June 2006
RCC placement in stage 2 at Yeywa
The RCC placement in Stage 2 of the dam at Yeywa was completed on 15 June. 268000 m3 of RCC has been placed in just over four months at an average rate of 64500 m3/month using only half of the concrete plant which has a nominal capacity of 480 m3/hour (i.e. only 240 m3/hour)

12th December 2004
River diversion at Yeywa
The Myitwge River -- a tributary of the Ayeyarwady -- was diverted through the diversion tunnels on 12 December, thus completing a further Stage of this important Project.
24th May 2005
First full-scale trial at Yeywa
The first full-scale trial at the Yeywa site has been successfully completed, investigating various options for joint treatment and various retarders. The trial was undertaken in temperatures that exceeded 40 C on most of the days.
22nd August 2005
The Second Full Scale Trial at Yeywa
The Second full-scale trial was completed at Yeywa. This was used to further train the DHP operatives and engineers in the procedures of RCC construction and also to investigate various retarders to extend the initial set of the RCC required 18 to 24 hours
24th January 2006
The Third (and final) full-scale trial completed at Yeywa
The Third (and final) full-scale trial was completed at Yeywa. The trial was used to train the operatives and engineers of CGGC, the newly-appointed Chinese Contractor for the construction of the dam body at Yeywa.
8th February 2006
First RCC Placement at Yeywa
The placement of the first RCC in the main body of the dam at Yeywa stated with a ceremony on 8th February 2006

Category:

Education

Tags:

License:

Standard YouTube License

  • likes, 1 dislikes

Link to this comment:

Share to:

All Comments (0)

Sign In or Sign Up now to post a comment!
Loading...

0 / 00Unsaved Playlist Return to active list
    1. Your queue is empty. Add videos to your queue using this button:
      or sign in to load a different list.
    Loading...Loading...Saving...
    • Clear all videos from this list
    • Learn more