Concrete & Block Koi Pond Clermont Florida
Loading...
2,598
Loading...
Uploader Comments (nationaleventphoto)
see all
All Comments (5)
-
NICE JOB ~ VERY TRANQUIL
-
where's the pond?
-
amazing... can i ask you guys how much it cost for the finish project? i live in orlando and i am trying to build one.. by the way you guys did an amazing job. enjoy.
-
Looks amazing
Loading...
Cost was $900.00, hand poured concrete floor 4 in thick, 80 bags of concrete, 70 4x8x16 blocks poured centers with concrete no rebar, then coated with a sand mix to give texture.. took 9 working days about 6-7 hours per day to complete, Location Clermont Fl
nationaleventphoto 1 year ago