In this video, Alan Shalloway describes the process of mapping a value stream to a Kanban board and why both are important in improving business-driven software development.
Avg Time Worked = .5 + .1 + 60 + 1 + 40 + 40 + 2 + 80 + 40 + 3 = 266.6 ~ 267 not 509. Is this correct? Just want to make sure I am added the right numbers.
How did you get the Avg Time Worked to equal 509? Are you adding the avg hrs in each box or something else? And what numbers do you add to get the Total Cycle time. Thanks!
you're not including the loop backs. they add
.2*(40+2) + 3 * .65 * (80+40) which is 242.4 hours.
alshall2 11 months ago
Avg Time Worked = .5 + .1 + 60 + 1 + 40 + 40 + 2 + 80 + 40 + 3 = 266.6 ~ 267 not 509. Is this correct? Just want to make sure I am added the right numbers.
theronandrew 11 months ago
How did you get the Avg Time Worked to equal 509? Are you adding the avg hrs in each box or something else? And what numbers do you add to get the Total Cycle time. Thanks!
theronandrew 11 months ago
How did you get the Avg Time Worked to equal 509? Are you adding the avg hrs in each box or something else? Thanks!
theronandrew 11 months ago