This video displays footage of the installation of the final replacement steam generator in Bruce A. A total of sixteen steam generators, each weighing 110 tonnes, were replaced in Units 1 and 2 in Bruce A. The first eight replacements in Unit 2 took 178 days to complete, and the final eight replacements in Unit 1 took only 76 days.