Level 2 concrete pour at Redcliffe, Qld for Soberon Developments.
This pour started at 3.00am and was completed by 4pm. Big Day..
There was over 810 Cubic metres of concrete and 113 tonne of steel to make up this deck.
Big thanks to the crew at Powercrete for providing the pumps, Boral for concrete and Chris Lawson for the hard working concretors. Of course a big thankyou to everyone else along the way.... Formwork, Steel Fixers, Plumbers, Electricians... wow!