Shillingstone 4th May 09; p-way progress. The target for this year is to lay 240 feet flat bottom on timbers through the up platform, move the diesel from the dock to the up main by Antell's lorry - excavate the down platform bed, lay terram and fresh ballast - build the foot crossing - rebuild the south up platform wall - move morning star back 90 feet north towards bath - bring in southern green mark 1 coach into cattle dock from long marston - bring in rail crane and bogie bolster - rebuild wickham trolley hut at down north platform ramp and bring in wickham trolley from clutton.