2 Bedroom
GDEGROUP
56 views
-
Anno Visser Studio
GDEGROUP
71 views
-
Larsson
GDEGROUP
81 views
-
Jens Karvonen
GDEGROUP
206 views
95% complete. Bathroom taps to be installed. Glass balcony to be installed. Stair bannisters and steel to be painted white and acacia wood steps to be installed. Painting t...
-
Fors&Kaz structural progress
GDEGROUP
48 views
-
Henson Apt
GDEGROUP
83 views
95% finished. Handles for kitchen and closets not installed. Glass for balcony not installed. Tap for Bathroom vanity, plus higher tiling in shower area
-
Picture 014.avi
GDEGROUP
78 views
Building 2 Structural Work
-
Picture 013.avi
GDEGROUP
41 views
Henson apt interior. plastering works, plumbing and electrical rough ins being completed
-
Picture 010.avi
GDEGROUP
86 views
Roadway and Rip-Rap
-
Building 1 update
GDEGROUP
111 views
Entry at the 4th floor and up the stairs to the top floor. Steelwork for columns and beams being put in place for the rooftop. Expect to pour the roof in 3 weeks.
Road cons...