  • can you please tell me what the meaning of optimitische duration, expected duration and pessismitic duration in theory? what are they? and in which condition should i use a duration weights? thanks in advance..

  • when you are planning the different tasks in a project, the optimistic duration is the duration in the best case scenario (likely a short duration), the expected duration is the most likely duration of a task, and the pessimistic duration is the duration in the worst case scenario. you would use it when you are uncertain of the length of time a task or activity will take. let me know if you have any other questions. thanks for watching

Loading...
Alert icon
0 / 00Unsaved Playlist Return to active list
    1. Your queue is empty. Add videos to your queue using this button:
      or sign in to load a different list.
    Loading...Loading...Saving...
    • Clear all videos from this list
    • Learn more